(1). Pre-installation recommendations

 

1. garage door must be able to be lifted and closed easily by hand and without much effort. a well balanced & sprung door is critical for proper installation.
2. the garage door opener can’t compensate for a badly installed garage door and should not be used as a solution for a “hard to open” door.
3. if the unit is being installed on an existing door, make sure any existing locking devices are removed or warranty will be void.
4. an approved outlet must be installed near where the opener is begin installed.
5. there should be a minimum gap of 30mm between the bottom ofthe chain drive rail and the top of the garage door at its closest point. (refer to figure 1 .)

 

important note: as for additional safety rules, we strongly recommends the fitting of photo electric safety beams on all installations.

 

pre installation recommendations

 

 

(2). Mount wall bracket and door bracket (figure 2)

wall bracket – close the garage door and measure the garage door width at the top and mark the centre. locate and mount the wall bracket 2cm-15cm above the door on the inside wall. (depend on the actual installation space).
door bracket – fix the door bracketto a structural part of the door as close to the top edge as possible.

 

mount wall bracket and door bracket

 

 

(3). Installation (steel track)

 

installation steel track

 

step1 (figure.3)
attach the opener head to the steel track. assembly the 2 “u” hanging brackets with 6mm nuts supplied.
step2 (figure.3)
place the steel track and opener head assembly centrally on the garage floor, with the open head furthest away from the door. lift the front of the track up to the door bracket. insert the pivot pin and secure it with the split pin supplied.
step3 (figure.3, figure.4)
install steel track
lift and support the opener head (with a ladder) so it is positioned centrally and level. fix the opener and track on ceiling by iron bracketa & b.

 

warning: do not allow children around the door, opener or supporting ladder serious injury and/or damage may result from failure to follow this warning.

 

installs steel track

 

step4 (figure.3, figure.5)
connect the straight arm to the bent arm with the bolt.
position and bolt the arms to the top edge of the door using the bolt supplied.

 

step5
lift the garage door until the shuttle locks into the drive chain/belt.
now, ready to program the openers.

 

(4). Sectional steel track assembly

 

First:
2-parts steel track: as figure.6, slide the a rail into the sleeve, slide the b rail into the sleeve.
2 parts steel track
3-parts steel track: as figure.7, slide the c rail into the sleeve, slide the d rail into the sleeve; slide the e rail into the sleeve.
3 parts steel track

 

Second:
cut the plastic thread; pull the screw rod along with inner chain to the end rail position (figure.8)
cut the plastic thread; pull the screw rod along with inner chain to the end rail position

 

Third:
as figure.9, release the nut & spring.
release the nut & spring

 

Fourth:
tightthe nut to the right position as shown in figure.10, cut the plastic tape, cut the plastic thread on sprocket, then whole rail assembled finished.
tightthe nut to the right position

 

(5). Installation (aluminium track)

 

installation aluminium track

 

step1(figure.12, figure.13)
insert the shuttle into the cut-out at the end of the aluminium track. be sure it faces the right direction (the disconnection arm on the shuttle faces towards the opener head). slide the shuttle along the rail until it locks into place with the brass chain coupler. move the whole shuttle assembly to the centre of the drive rail.

 

arm transport shuttle, chain drive rail
arm transport, brass chain coupler

 

 

step2 (figure.14)
using the 6mm hexagon head rail mounting bolt supplied, slide 2 bolts in each side of the rail through the cutouts provided.
mounting operator from rail

 

step3 (figure.11)
attach the opener head to the steel track. assembly the 2 “u” hanging brackets with 6mm nuts supplied.

 

step4 (figure.11)
place the aluminium track and opener head assembly centrally on the garage floor, with the open head furthest away from the door. lift the front of the track up to the door bracket. insert the pivot pin and secure it with the split pin supplied.

 

step5 (figure.11)
lift and support the opener head (with a ladder) so it is positioned centrally and level. fix the opener and track on ceiling by iron bracket a & b.
warning: do not allow children around the door, opener or supporting ladder serious injury and/or damage may result from failure to follow this warning.

 

step6 (figure.11)
select and attach the straight arm and bend arm. position and bolt the arms to the top edge of the door using the bolts supplied. lift the garage door until the shuttle locks into the drive chain.

 

now, ready to program the openers.

 

(6). Battery backup assembly (optional)

 

Option 1 – top fixed

 

step1 (figure.15)
assemble the battery & battery bracket like the photo, fix by screws supplied.
top fixed battery & battery bracket step1

 

step2 (figure.16)
join the battery to opener, find the figure.12.
top fixed battery & battery bracket step2

 

 

Option 2 – side fixed

step1 (figure.17)
assemble the battery & battery bracket like the photo, fix by screws supplied.
side fixed battery & battery bracket step1

 

step2 (figure.18)
join the battery to opener, find the figure.14.
side fixed battery & battery bracket step2